Construction project not subject to the standard permitting process; application for an exemption during a moratorium on changes to ensure compliance with urban planning regulations
Brief description
Are you planning a construction project on a property that does not require a building permit, but is currently subject to a moratorium on changes to ensure compliance with land-use planning regulations? If so, you can apply for an exemption, provided that no overriding public interests preclude it.
Description
Construction projects that do not require a building permit are those that do not require a building permit. You may proceed with construction as long as there is no moratorium on changes.
However, for your construction project that does not require a permit, you may be granted an exemption from the moratorium on changes intended to safeguard urban land-use planning, provided that there are no overriding public interests that would preclude it. The building permit authority, in consultation with the municipality, will decide whether to grant your exemption.
Examples of public interests:
- Historic Preservation
- Nature Conservation
- Environmental Protection
- Townscape and Landscape
The following may be affected by a change freeze:
- Construction, alteration, or change of use of structures,
- Large-scale earthworks and excavations,
- Excavations, deposits, including mineral deposits,
- Removal of Structures
- significant or substantial improvements to real property and structures, provided that such improvements are not subject to approval, consent, or notification requirements.
The following are not affected by the change freeze:
- Projects that were approved under building codes before the moratorium on changes took effect.
- Projects of which the municipality is aware and for which construction could have begun before the moratorium on changes took effect.
- Maintenance work and the continuation of a previously established use.
For Construction Projects
- in officially designated redevelopment areas or
- in the urban development area
Different regulations apply than those for construction projects affected by a moratorium on changes intended to safeguard urban land-use planning. In such cases, the construction project must have been approved by the municipality.
Prerequisites
Statewide Addendum
You are planning a construction project on a property that does not require a building permit, but which is currently subject to a moratorium on changes to ensure compliance with land-use planning regulations.
Deadlines
Statewide Addendum
noneCosts
There are no costs involved.
Legal basis
Legal remedy
- Objection
Procedure
Statewide Addendum
You must apply to the relevant municipality for an exemption from the moratorium on changes to ensure compliance with the land-use plan.
Notes
There are no notes or special considerations.